MacEwan University – Alberta College at Allard Hall

L5 1 Allard Hall - Fifth Floor

Allard Hall – Fifth Floor, complete fit out of 6,000 sq m floor plate for Alberta College including new stair, two new AHUs, 18 classrooms, two learning labs,  chemistry, biology, and physics labs, a business learning centre, reception, registration,  and administration areas.

A new 70 ft steel and concrete stair was inserted over an existing atrium between floors 4 and 5 and an innovative use of custom length fire shutters – up to 40 ft long – was used to maintain code compliance.  We created a colegial work team between the client, the contractor, subtrades, and the consultant team enabling the $13M project to come in on time and under budget.

Client:

MacEwan University, Edmonton, AB

Contractor:

Clark Builders

Engineering:

Structural- Fast and Epp, Mechanical -HRC Engineering, Electrical – MP&P,, Code – LMDG, QA – FSC, Roofing – Regional Roof Inspections

Cost:

$13.0 M

Span:

Design begun Feb 2019. Construction complete July 2020